Main Street Improvement Project

MAIN STREET IMPROVEMENT PROJECT INFORMATION

UPDATES 

Tasks Completed:

9/3 – 9/26:  Installation of SCWA new water main

9/16 – 10/1:  Removal of all asphalt paving, curbs, concrete road base and landscaping

9/16 – 10/15: Installation of SCWA tie-overs and retirements

9/30 – 10/9:  Excavation and removal of unsuitable soil from entire length of road

9/30 – 10/4:  Installation of drainage pipes, catch basins and leeching pools east of

Mill and west of Mitchell

9/30 – 10/12: Removal of all drainage structures

10/9-10/14: Dry sewer main installed between Sunset and Moniebogue

10/7-10/25: Removal of additional unsuitable soil by bakery.

10/14-11/1: Drainage installation between Mill and Mitchell.

10/10-11/1: Conduit for electric and Verizon from Potunk Land to Glover’s Lane.

10/21-11/5: Curbing for Potunk Lane traffic circle and curbing from Potunk Lane to Moniebogue Lane.

11/5/19  Binder course of pavement from Potunk Lane to Moniebogue Lane complete.

11/23/19 Pavers and checkerblock installation at Potunk Traffic Circle complete.

11/25/19 Drainage and conduit for underground utilities complete, with the exception of Beach Lane crossing.

 

Two-week look ahead:

Concrete curb from Glovers Lane to Beach Road – expected completion on or about December 2nd.

Sidewalk removal, preparation and installation from Potunk Lane to Mitchell Road in progress.

Crossing from Sunset to Moniebogue will be closed from December 2 to December 5th for the installation of crosswalk pavers.

Curbs for traffic circle at Mill/Library, and roadway curbs from Mill to Beach-expected completion on or about December 11th.

For SCWA information, call 631-698-9500

For all other information, call 631-287-6000.

Click Here to View Proposed Main Street Streetscape

 

Click Here to View Funding Secured as of June 2019

Click Here To View Existing Drainage Pipe Conditions

Click Here to View Roundabouts-H2M

Click Here to View Roundabouts-US Department of Transportation